Historic Building Renovation
This renovation of a downtown Tallahassee historical building included demolition and skeletal build out
- CLIENT White House Fellows
- YEAR 2005
- WE DID Construction Management
- PARTNERS Clemons Rutherford
- CATEGORY Commercial
Carriage Gate Shopping Center
This new construction project was a design build/Construction Management project that was completed on time and within budget. This commercial retail building consists of 14 retail units located in McDonough, GA
- CLIENT Shumard LLC
- YEAR 2005
- WE DID Construction Management, Design Build
- CATEGORY Commercial
Elinor Doyle Building Renovation
This renovation of a downtown Tallahassee historical building included demolition and interior build out. The first floor is now home to Elinor Doyle Florists and the second floor is occupied by a private firm.
- CLIENT Paul Bradshaw
- YEAR 2005
- WE DID Construction Management, Renovation
- CATEGORY Commercial
Historic Home Renovation
Southland provided interior renovations for the 2nd floor offices of Core Message. Careful consideration and methods were used in the renovation process due to the historic nature of the building.
- CLIENT Core Message Inc.
- YEAR 2003
- WE DID Construction Management
- CATEGORY Residential
Superior Learning Academy
Superior Learning Academy is a private school facility located in McDonough, Georgia. The building is 8,000 square feet.
- CLIENT B.E.C. Properties & Holdings
- YEAR 2003
- WE DID Construction Management, Design Build
- CATEGORY Commercial
Corporate Center
The Corporate Center Office Buildings are located in McDonough, Georgia. This project consists of two 18,000 sq ft buildings each being three stories. Each building has a steel structure and veneer brick exterior. The buildings are privately owned and have executive office build-outs throughout.
- CLIENT B.E.C. Properties & Holdings
- YEAR Completed 2003
- WE DID Construction Management, Design, Build
- PARTNERS Architecture By Design
- CATEGORY Commercial
Capitol Security Upgrades
This project was a Design Build with DMS and Southland. Phase 1 consisted of constructing a 10” X 10” X 8” CMV wall guard house and installed approximately 70’ of concrete barrier. Phase 2 consisted of installing a 4-6’ diameter fixed bollards, force protection barrier and 40’ concrete barrier wall. Phase 3 consisted of installing
- CLIENT State of Florida Department of Management Services
- YEAR 2002
- WE DID Design Build
- CATEGORY Commercial
Knott Building Walkway Renovations
Southland Contracting, Inc. installed a new sloped walkway to meet ADA requirements. Along with the sloped walkway, Southland Contracting, Inc. also fabricated and installed new railings and new carpet. This project was done in a 14 day time period over Christmas Break.
- CLIENT State of Florida Department of Management Services
- YEAR 2001
- WE DID Construction Management
Carlton Building Computer Room Renovation
This project entailed demolition of the existing computer rooms and returning the space to offices. The project included asbestos abatement, halon gas, leibert, and raised flooring removal. DMS had funding issues that SCI worked within. We found ourselves working with a DMS Mechanical C.M. as a sub and as the prime C.M. for coordination purposes.
- CLIENT State of Florida Department of Management Services
- YEAR 2001
- WE DID Construction Management
- PARTNERS McGinnis & Fleming
- CATEGORY Commercial